Initial page
for our documentation of the saving of the historic Hampden Bridge in Wagga
Wagga. (Technical
details in the form of a paper are being produced and will be posted later).
We use the term
saving as when we were commissioned by the Wagga Wagga City Council for
inspection and advice on what to do with the bridge, all the experts who had
investigated the Hampden Bridge indicated that the bridge was unsafe and needed
to be demolished.
The bridge
had been superseded by a modern concrete bridge a number of years ago and the
Hampden Bridge was left in its original state, as when it was made redundant.
In 2007 the bridge suffered a major partial failure due to one of the main
timber chords failing due to extensive attack by white pocket rot and the
photographs show the failed area 0.5 meters below its original profile.
The top deck view of the bridge indicating the partially
failed span in 2007.

Side view
shows the dramatic collapse

Reference
picture

Background
The
See www.integritytesting.com.au/papers
The failed chord
indicating the approximately 0.5 meters of white pocket rot which caused the
partial failure of the bridge and the initial cleaned section.
|
|
|
Integrity Testing
Pty. Ltd were commissioned to give advice to the client on what they should do,
either demolition or preserve the bridge. Initially Integrity tested the bridge
using their DBTS™ system to measure the remaining capacity in the bridge. The
results showed there was sufficient residual capacity to facilitate a fix. The
method of the fix was to replace the stumps in the shoes with steel section
rather than replace the whole failed chord. There was also the problem that
large hard wood timber was scarce.
The table of capacities gives gross vehicle mass for three types of trucks and their principle wheel configurations. The method employs an equivalent beam method to calculate the present capacity of the bridge. Effectively the truss acts as a large beam with the top and bottom chords acting as flanges to this equivalent beam. The DBTS™ method is extremely accurate with a five order of magnitude accuracy better than the conventional static load testing.
|
Span |
EI N.m2 |
Total Load KN |
Moment Capacity KN. m |
B-double GVM Triple or Quad Axles |
T-44 GVM Tandem Axles |
Rigid Truck GVM Single axle |
Pedestrian Traffic As a Crowd |
|
1 |
1.05 x 1010 |
300 |
1080 |
N/A |
N/A |
N/A |
18% * |
|
2 |
1.68 x 1010 |
1180 |
4970 |
66t |
44t |
18t |
95% |
|
3 |
1.50 x 1010 |
920 |
3890 |
52t |
44t |
18t |
75% |
Budgets for
this work was limited, but luckily Wagga Council were able to procure a
launching beam, Integrity recommended preservation and by means of modifying
the beam launching frame (Used to launch the beams for the new Hampden Bridge)
with which the bridge was restored to its original line and level.
View of re
stumped section
|
|
|
Eventually
the steel boxed sections will be covered in a timber veneer.
The bridge
after completion of the lifting showing the lifting frame and the new level
line of the bridge.

The bridges line and level restored. See along the line of
the hand rail.

The soffit
of the bridge indicating how much the deck was raised and that the deck was not
relying on the support frame.

The aim of the works was to make the bridge safe, through ingenuity, value engineering with sound Engineering practices the Bridge is now considered safe and the client is investigating ways to fully preserve the bridge as a tourist attraction.
Our gratitude and thanks go to the staff of Wagga Wagga City Council and in particular Lindsay Tanner and Bryan Short who had the faith in us to save the bridge. It was jointly their management of the project and Integrity Testing’s engineering input in particular its Director John Higgs that saved an historic bridge, with the costs being considerably less than half of the cost for demolition.
Copy of original Drawing

More info can be found at www.integritytesting.com.au and
follow the link to contact us.